Find out how on
Two FREE MUST HAVE guides:
A process to determine the exact space requirements and needs of an office occupier, including: storage, breakout space, private offices, meeting rooms, AV, AC, IT, alarms, access security, etc.
Air conditioning
Reduce noise levels between areas
Audio/Visual
A two-dimensional drawing usually showing layouts of workstations, lighting, ceilings, etc.
A three dimensional lifelike drawing often produced from a two-dimensional drawing using sophisticated software, or alternatively hand drawn.
A plan of where departments will be situated within a building.
An area designed for staff to meet or relax away from their desks, ideally equipped with informal seating, tables and refreshment facilities.
A report listing what is involved in a project and how much it will cost to complete.
An approval that the drawings submitted conform to the current Building Regulations, given by a local authority or qualified person.
Computer Aided Design.
Office space fitted out to a standard where toilets, lifts etc. are operational and décor neutral.
Office space fitted out ready for occupancy by staff, with all furniture and décor complete.
The Construction (Design & Management) Regulations 2007 (CDM 2007) came into force on
6th April 2007. Objectives:
The refurbishment of space that is already in use, but a change of use or more efficient use of space is required.
When all personal items must be returned to storage at the end of a period of use of a workstation.
Space within a building used by all staff / tenants, such as main reception, stairwells and wash rooms.
Disability Discrimination Act 1995 (c. 50)
An Act to make it unlawful to discriminate against disabled persons in connection with employment, the provision of goods, facilities and services or the disposal or management of premises; to make provision about the employment of disabled persons; and to establish a National Disability Council.
An area, either in the same building or an alternative location, where staff can be temporarily housed while work is undertaken.
What does the term Rw mean when it appears after a decibel rating i.e.: 45dB Rw
This was set out under the British Standards in order to harmonise the comparison of products that were acoustically tested. The term Rw refers to the "Weighted Sound Reduction Index" and this is a figure calculated for a set of results measured over a specific set of frequencies that are "Weighted" to most closely represent the normal response of the human ear to sound. In America the standard is called the Sound Transmission Class (suffix STC) and is calculated over a slightly wider frequency range using a similar principle.
The time span following completion of a project that the main contractor is responsible for any defects/snags.
Easy to dismantle and re-erect.
A fit-out or refurbishment project where the design and construction are undertaken by the same company.
A fit-out project where work is undertaken from a client’s specification and a design team is not required.
Keeping up with ever changing rules & regulations to ensure compliance on sites.
(See RRFSO below)
A tradesman responsible for controlling specific sections of the work.
A project to develop an internal space into a state fit for its intended use.
A terminal with sockets for power, data and telephone connections.
Health & Safety Executive
A manual containing details of all products used in the construction and information on subsequent maintenance procedures required.
Heating, ventilation and air conditioning.
A shared desk space, not allocated with one permanent user.
A letter confirming that it is the intention of the client to enter into a contract, usually subject to conditions.
A contractor’s proposal for a project giving an overall cost for all works.
Work involving heating, air conditioning, power and lighting etc.
The company that undertakes the planning, co-ordination and management of a project.
The co-ordination and management of moving staff and/or equipment between offices and/or sites.
To instruct the main fit-out contractor to use the services of a particular professional.
An instruction manual, kept on site, for services that have been installed on site.
An agreement where all costs (and cost savings) are completely transparent between the principle contractor and the client often used when the costs are likely to fluctuate and the profit for the contractor is pre-agreed.
A consent given by a local authority to construct a new structure or make visible changes to an existing structure, or change the use of a building.
The day when a project is fit for beneficial use by the client.
The person responsible for the day-to-day running of a project.
The contractor responsible for health and safety during works, usually the main contractor.
A project to renew space that has been used at some time, either to be renewed for a similar purpose or to prepare it for a change of use.
The re-design and fit-out of existing office space to allow for an increased number of occupants.
Regulatory Reform (Fire Safety) Order 2005
The Regulatory Reform (Fire Safety) Order made in June 2005 was due to come into force in April 2006 was deferred to October 2006 to give businesses and stakeholders more time to prepare. Fire Certificates are to be abolished and will cease to have legal status.
Instead, if responsible for a business premises, an employer, self-employed with business premises, a charity or voluntary organization or contractor with a degree of control over any premises, then fire precautions will need to be put in place “where necessary” – to extent that is reasonable and practical in the circumstances of the case.
The document describing the condition of a building at the beginning of a lease.
The document describing the state of disrepair of a building which the landlord or tenant must put right at the end of a lease.
Written details of all works involved in a project.
A permanent foreman on site to co-ordinate and take responsibility for day to day site management, including health and safety.
The process where information about an organisation is gathered and analysed to produce a plan for accommodating staff.
The removal of internal fixtures and finishes from a building.
A specialist company or tradesman employed by the principal contractor to carry out works.
The process and documents used by a client to select a principle contractor for a project.
A workstation available for short periods of work with access to email etc.
A fit-out or refurbishment where the client appoints a design team, a project management team and other professionals and the contractor is finally selected by means of a tendering process.
First amount tendered will reflect the principal contractor’s management fee only for the project. The principal contractor is then appointed on this basis and the second stage tendering will then include sub-contractors costs for works.
Where all elements of a project are supplied through one company.
Wherever there is an alteration or amendment to a previously agreed design, layout or construction detail on site, the Contract Administrator (CA) will issue a VO to the contractor responsible for carrying out the works along with a request for additional costs (if any) for including the works within the agreed programme. (Copied to client)